Scheduling

Fall Semester Schedule

No Items Start Date End Date
1 Camera Calibration 11/9/2016 11/13/2016
2 Object Detection 10/21/2016 11/9/2016
3 Stereo Vision Capture 11/3/2016 11/9/2016
4 Relative Distance Estimation 11/9/2016 11/18/2016
5 Litter Classification 11/14/2016 12/10/2016
6 Arm 11/1/2016 12/1/2016
7 Learn Joint Calibration Steps 11/1/2016 11/7/2016
8 Use Basic Windows GUI 11/1/2016 11/7/2016
9 Aquire ROS Packages 11/8/2016 11/11/2016
10 Publish Joint Angles 11/12/2016 11/22/2016
11 Interface with MoveIt 11/12/2016 11/22/2016
12 Inverse Kinematics 11/23/2016 11/29/2016
13 Server Data Interface 10/21/2016 10/29/2016
14 App 10/30/2016 11/13/2016
15 Data Collection 11/14/2016 11/24/2016
16 System Integration 11/25/2016 12/5/2016
17 Point Cloud Interpretation 10/21/2016 10/29/2016
18 Output Obstacle Detection 10/30/2016 11/8/2016
19 Drive System 10/21/2016 10/29/2016
20 GPS Integration 11/7/2016 11/25/2016
21 Heading calculation 11/11/2016 15/11/2016
22 Heading control 11/7/2016 11/11/2016
23 Position calculation 11/15/2016 11/19/2016
24 Position control 11/19/2016 11/25/2016
25 GPS Waypoint 11/8/2016 11/13/2016
26 Zg Zag Strategy 11/8/2016 11/10/2016
27 Waypoint calculation 11/10/2016 11/13/2016
28 Movement 11/11/2016 11/24/2016
29 Motor control commands 11/11/2016 11/14/2016
30 TF Tree 11/14/2016 11/19/2016
31 Path Plan Changes 11/9/2016 11/24/2016
32 Choose turning direction and Movement 11/10/2016 11/17/2016
33 Send Desired Movements to PID 11/15/2016 11/25/2016

Spring Semester Schedule

No. Item Start Date End Date
1 Revamped Physical Structure Complete 1/20/2017 2/3/2017
2 Navigation Improvement 2/3/2017 2/17/2017
3 Investigate visual odometry 1/20/2017 2/10/2017
4 Nav & obstacle avoidance integration 2/17/2017 3/3/2017
5 Classifier training and data collection 2/17/2017 2/24/2017
6 CV Classification 2/24/2017 3/3/2017
7 Navigation and CV integration 3/10/2017 3/17/2017
8 Remote Start Stop complete 3/24/2017 3/31/2017
9 Activate End Effector 1/30/2017 2/20/2017
10 Release Litter 3/3/2017 3/8/2017
11 Path Plan to Bin 2/27/2017 3/9/2017
12 End effector design and fabrication 1/15/2017 2/13/2017
13 System Integration 1/20/2017 4/14/2017
14 Tests 4/7/2017 4/14/2017