Schedules

Progress review presenters (Fall)

DateProgress Review No.Presenter
Sept 10, 2025Progress Review #7Swastik Mahapatra
Sept 24, 2025Progress Review #8Amy Jiang
Oct 8, 2025Progress Review #9Abhishek Iyer
Oct 29, 2025Progress Review #10Aayush Fadia
Nov 12, 2025Progress Review #11Ranai Srivastav
Nov 17, 2025Fall Validation Demonstration (Progress Review #12)All
Nov 24, 2025Fall Validation Demonstration Encore (Progress Review #13)All

Progress review presenters (Spring)

DateProgress Review No.Presenter
Feb 6, 2025Sensors & Motors LabRanai Srivastav
Feb 13, 2025Progress Review #1Aayush Fadia
Feb 27, 2025Progress Review #2Abhishek Iyer
Mar 20, 2025Progress Review #3Amy Jiang
Apr 3, 2025Progress Review #4Swastik Mahapatra
Apr 17, 2025Spring Validation Demonstration (Progress Review #5)All
Apr 24, 2025Spring Validation Demonstration Encore (Progress Review #6)All

Work Schedule (Fall)

Gantt chart

Test Plans

Fall Test Plan

Spring Test Plan

Spring Validation Demonstration

Parts List

The linked sheet tracks all parts purchased by the team.

Issues Log