Schedules
Progress review presenters
Date | Progress Review No. | Presenter |
---|---|---|
Feb 6, 2025 | Sensors & Motors Lab | Ranai Srivastav |
Feb 13, 2025 | Progress Review #1 | Aayush Fadia |
Feb 27, 2025 | Progress Review #2 | Abhishek Iyer |
Mar 20, 2025 | Progress Review #3 | Amy Jiang |
Apr 3, 2025 | Progress Review #4 | Swastik Mahapatra |
Apr 17, 2025 | Spring Validation Demonstration (Progress Review #5) | All |
Apr 24, 2025 | Spring Validation Demonstration Encore (Progress Review #6) | All |
Gantt chart

Test Plan
Spring Test Plan
Spring Validation Demonstration
Parts List
The linked sheet tracks all parts purchased by the team.
Issues Log
Key design issues and important decisions are tracked in Slite.