Issues Log

IssueDescriptionMitigation / ResolutionStatus
Unity SimulationUnity Hub simulation environments are failing to initialize or perform reliably.Bypass Simulation: Transitioning directly to physical “on-robot” testing to maintain development velocity.🟢 Resolved
GNSS-RTK AccuracyGlobal Navigation Satellite System (GNSS) positioning was drifting and lacked precision.Base Station Alignment: Fixed by aligning and syncing the GNSS system with the AirLab base station.🟢 Resolved
Compute ConstraintsJetson Nano hardware is potentially insufficient for simultaneous high-load tasks.Sequential Processing: Restructured navigation and perception algorithms to run without overlapping compute cycles.🟡 In Progress
Timeline SlippageProject is currently behind the original schedule due to hardware and integration delays.Increased Oversight: Implementing shorter-term milestones, frequent sync meetings, and Kanban-style management.🟡 In Progress
Arm Safety (E-Stop)The xArm e-stop is currently independent/inactive relative to the main system.Integrated Safety: Hardware integration of the xArm e-stop into the main Warthog platform emergency circuit.🔴 Pending
Supply ChainDelays in receiving ball screw connectors, 80/20 extrusions, and fasteners.Procurement Sprint: Finalized budget and BOM; currently tracking shipments and sourcing local fasteners.🟡 In Progress