Spring 2022
Here is a list of the top 6 risks we identified with our project.
Risk 1 (highlighted in green) is no longer a matter of concern since our drone arrived on time, and we have finished constructing and testing it as well.
Fall 2022
As we progressed into the Fall semester, we identified new risks in our project. The active risks have been tabulated below.
As we were mid-way into our project we revisited our risks and we identified that some risks no longer apply to our project. Tabulated below are the risks that were retired this semester.
Here is the Likelihood-Consequence table before and after risk mitigation.