VectorRobotics

    • Documentation
    • Gallery
    • Project Management
      • Risk Management
      • Schedule
    • System Design
    • System Implementation
      • Control Sub-system
      • Navigation Sub-system
      • PCB Design
      • Perception Sub-system
      • System Interface
    • Team
    • Video Demos

Risk Management

Risks identified in the Spring:

we have identified and continuously monitored key risks that could affect the progress of our project. These risks span both technical and logistics domains. The risk matrices outline each identified risk along with its likelihood, severity, and planned mitigation approach. In general, our mitigation are mainly designed to reduce the likelihood of all the risks identified. The majority of the risk will be under control as the project proceeds as planned. The risks are listed below.

Risks identified in the Fall:

The Fall 2026 risks below summarize the team’s risk register and subsequent project updates through September 25, 2026. They cover technical reliability, integration, resources, and delivery. Current status distinguishes ongoing risks from mitigations already reported.

Likelihood and consequence ratings are omitted pending review. Expected outcomes are mitigation objectives, not verified results.

Technical — Button Pressing and Skill Chaining

Risk register: R-05, R-19
DescriptionUnreliable button presses or brittle transitions between skills can prevent a complete elevator mission.
Root CauseButton-localization errors, stale robot poses, planning latency, and variation in the robot’s final walking pose.
ConsequenceIndividual skills may work in isolation while the complete mission fails.
Current StatusActive. September 22 tests still showed button-dependent reliability: 1 of 7 lower-button presses and 6 of 7 upper-button presses succeeded. End-to-end reliability remains to be demonstrated.
Mitigation Strategy
ActionExpected Outcome
Improve calibration, track time-tagged trajectories, run manipulation on the NUC, and refresh the base pose within one second of arm motion.More repeatable button contact and less error from delayed state estimates.
Retain fixed-floor chaining and a demonstration-site detector fallback; demonstrate difficult skills separately if necessary.Preserve a demonstrable baseline while integrated reliability improves.

Technical — Perception and Localization Accuracy

Risk register: R-09, R-13, R-21
DescriptionUnstable detections, orientation error after walking, or camera-to-robot transform error can displace the estimated button target.
Root CauseDetection variability, imperfect extrinsic calibration, and differences between the planned and actual robot pose.
ConsequenceThe robot may approach the wrong contact point or lose a usable view of the panel.
Current StatusActive. Calibration has been revised, but repeatable button-position errors in later hardware tests still require investigation.
Mitigation Strategy
ActionExpected Outcome
Use object tracking and multi-frame agreement before solving the arm motion; use visual feedback to correct alignment.A more stable target estimate and better alignment before contact.
Refine and validate camera-to-robot calibration; retain manually tuned or CAD-derived extrinsics as a fallback.Reduce systematic target offsets across the perception and manipulation pipeline.

Technical — Communication and Compute Performance

Risk register: R-04, R-10
DescriptionLoss of connectivity or excessive processing latency can interrupt perception and control during the elevator mission.
Root CauseDependence on external compute and processing stages that cannot meet the required update rate.
ConsequencePerception may stop during the ride, or control may use readings that are too old.
Current StatusPartly mitigated. Local deployment and VLM benchmarking have progressed. Tracking speed was reported as no longer a blocker on September 25; integrated performance still needs validation.
Mitigation Strategy
ActionExpected Outcome
Run inference locally and allocate perception and manipulation workloads to suitable processors.Reduce dependence on external Wi-Fi and lower processing delays.
Keep the IMU-based floor-detection pipeline available as a fallback.Maintain floor estimation when vision or its communication path is unavailable.

Schedule — Development and Module Integration

Risk register: R-01, R-02
DescriptionNew capabilities or separately developed modules may not converge and integrate before the final demonstration.
Root CauseUncertain development effort and dependencies between module interfaces, testing, and integration.
ConsequenceThe team may have working components without a complete, demonstrable mission.
Current StatusActive. The baseline mission and the integration of additional capabilities must be evaluated separately.
Mitigation Strategy
ActionExpected Outcome
Define module interfaces and use recorded data and simulation as shared validation references.Expose integration mismatches before full hardware testing.
Use a development checkpoint and reserve the final month for the baseline; fall back to fixed-floor chaining or a separate module demonstration where needed.Protect time for a demonstrable elevator mission if additional capabilities are not ready.

Personnel and Schedule — Team Availability

Risk register: R-07
DescriptionCoursework and project deadlines compete for the team’s available engineering time.
Root CauseTwo concurrent courses and fluctuating availability across team members.
ConsequenceTesting, integration, and documentation may slip during overlapping deadlines.
Current StatusOpen. As of the September 25 update, the register still had no assigned risk owner or agreed mitigation.
Mitigation Strategy
ActionExpected Outcome
Scheduling agreement and risk ownership: to be confirmed by the team.A documented allocation of time and responsibility across overlapping deadlines; not yet established.

Logistics — Hardware Availability and Test Conditions

Risk register: R-03, R-06, R-16
DescriptionUnavailable equipment, component failure, or restricted test access can reduce hardware-validation time.
Root CauseShared robot use, motor or sensor faults, and constraints around the test environment and public access.
ConsequenceFewer representative trials and delays in diagnosing or reproducing failures.
Current StatusUnder review. Moving to the RIC service elevator reduced booking and permitted-hours constraints. Hardware availability and the earlier breakdown-risk assessment still need review.
Mitigation Strategy
ActionExpected Outcome
Maintain spare parts and vendor support, and use redundant sensors where practical.Shorter interruptions when a component becomes unavailable.
Use the RIC test venue and complement robot trials with recorded-data and simulation tests.More predictable access and continued validation when hardware testing is limited.

Programmatic — Deliverable and Stakeholder Alignment

Risk register: R-08
DescriptionThe delivered capabilities or demonstration may not match advisor and sponsor expectations.
Root CauseChanges in project scope and different expectations for technical progress and the final deliverable.
ConsequenceA technically useful result may not satisfy the intended evaluation or sponsor outcome.
Current StatusActive. Keep the final deliverable aligned with the engineering baseline and the agreed demonstration scope.
Mitigation Strategy
ActionExpected Outcome
Build on the Spring stack, retain the engineering core, and show progress at two-week intervals.Earlier feedback on scope and clearer evidence of progress.
Maintain a strong demonstration video as a documented fallback deliverable.A clear, reviewable record of achieved system capabilities.

VectorRobotics

Proudly powered by WordPress